Aluminium Show|Danjiang Aluminum Industry's Battery Aluminum Foil Billet Project Engineering Marks Another Key Milestone
On March 20th, Danjiang Aluminum Company's battery aluminum foil billet project engineering reached another key milestone as the foundations for the melting furnace and the holding furnace were successfully poured, marking the transition of upper structure construction into a new phase and laying a solid foundation for the subsequent equipment installation and construction.
The foundation construction for the casting and rolling machine, melting furnace, and holding furnace in the casting and rolling workshop is a critical component of the project construction. The construction of these equipment foundations is complex, involving large volumes of concrete, a variety of embedded parts, high precision requirements, and significant construction challenges.
To ensure the foundation concrete is poured on schedule, the project construction command's engineering department worked closely with all participating units, organizing multiple inspections and acceptance checks before the concrete pouring by construction unit engineers, department professionals, and supervisory engineers. Any issues identified were addressed and rectified one by one. By continuously optimizing the civil engineering construction plan and meticulously planning the key construction processes, the project aims to ensure the subsequent equipment foundation concrete pouring work advance efficiently and to high standards.
According to Aluminium Show, the project construction command is currently seizing the opportune moment to strengthen the control over the entire construction process. With a determination to win, a sense of urgency, and solid and effective measures, they are fully committed to ensuring the project is delivered on time and with high quality.